SAW-GEO activities are governed by the schedule outlined in the Project Plan. There are 7 work packages timetabled as follows:
- Examining existing technologies - Oct 2006-Dec 2006
- Architecture design - Jan 2007-Mar 2007
- Implementation (inc. initial testing) - Apr 2007-Oct 2007
- Evaluation (inc. user testing) - Nov 2007-Dec 2007
- Revised implementation - Jan 2008-Feb 2008
- User training and dissemination - Mar 2008
- Reporting - Apr 2008